Commercial Building Energy Storage Project

Release time: 2026-09-07

Project Background

A commercial building required an energy storage system to better manage its electricity consumption while increasing the utilization of available renewable energy.

The building’s electrical demand varied according to business hours, HVAC operation and other commercial loads.

Customer Challenge

The building faced:

  • Variable daily electricity demand
  • Peak-period electricity consumption
  • PV generation and building load mismatch
  • Need for centralized energy monitoring
  • Limited flexibility in conventional power management

System Configuration

  • 300 kW Energy Storage System
  • 626 kWh Battery Capacity
  • PCS
  • EMS
  • Commercial building loads
  • PV integration capability

Higre Technology

Higre combined PCS power conversion with EMS energy integration.

The EMS coordinates energy dispatch and supports demand management and peak-load optimization.

Project Deployment

The system was integrated into the building’s existing electrical distribution architecture.

The modular design enables standardized installation and simplified commissioning while reducing the need for extensive modifications to existing infrastructure.

Deployment Result

The project provides the commercial building with:

  • Flexible peak-load management
  • Improved PV utilization
  • Intelligent energy dispatch
  • Centralized monitoring
  • Enhanced energy flexibility